Hampton Ltd Construction Update
Hampton Ltd, Hampton
August Construction Update
30 August, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for August 2026.
Mostly notably this month;
Building A is well progressed, with fit-off now underway across all trades, including plumbing, electrical, mechanical, fire services, joinery, and fixtures and fittings.
Balcony waterproofing to Building A is complete, ahead of pod paver installation and balustrading, both commencing shortly.
The Building B light gauge steel frame is now complete, with scaffolding wrapped around the entire perimeter ahead of window installation, cladding, and roofing. Windows are on site and ready for installation.
Ground floor rough-in to Building B has begun, with mechanical, plumbing, and fire services nearing completion at this level.
Ground floor plaster installation to Building C is complete, including stopping up, sanding, and the first coat of primer.
Ground floor joinery installation to Building C is well underway, with Levels 1 and 2 to follow shortly.
Plaster throughout Level 1 of Building C is nearing completion, and Level 2 is also well advanced, with fire-check party walls currently being finalised.
Kingspan insulation has been fitted to all Building C roofs, and ceiling grids have been installed ahead of plaster installation shortly.
Rough-in to Building C is also nearing completion, with the final elements on Level 2 now being finished.
The lifts to Buildings A and C have been officially completed by Forte Lifts and are now operational.
The display container has been removed as we enter the final stages of completing our prototype in Apartment 207.