Hampton Ltd Construction Update
Hampton Ltd, Hampton
June Construction Update
30 June, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for May 2026.
Mostly notably this month;
- Balcony Soffits of Building A have been rendered
- Balcony Floors in Building A have been waterproofed and are ready for pod and paver installation
- Hebel installation for Building A is complete
- Rendering of all external walls of Building A has commenced
- Building B's first-floor frame, including intertenancy walls, has been completed. The second storey posi's have been installed and yellow tongue flooring for level 2 is now commencing
- Exterior metal cladding on the 2nd floor of Building A has been completed
- The lift carts for Building A & C are well underway
- Scaffold has been erected around the perimeter of Building C in preparation for cladding
- Equipment for the fire pump room has been delivered to site
- Metro Civil has completed all external outfall drain works (stormwater) connect-ing our development to Council's LPOD.
- Shower screens in Building A have been installed
- Carpentry fix has begun in Building A, including the installation of door jambs, doors and skirting.
- Painting In Building A has also commenced, with all surfaces primed and ready for additional coats.
- Electrical cut-out work in Building A is complete
- Flooring throughout Building A has commenced
- Plaster installation on the ceilings of Building C's ground floor has commenced
- Laser Battens have been installed on Level 1 of Building C in preparation for ceiling plaster installation.