Hampton Ltd Construction Update
Hampton Ltd, Hampton
March Construction Update
28 April, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for March 2026.
Mostly notably this month;
Waterproofing and Tiling has begun in the wet areas of Building A
Wall and Ceiling Insulation for Building A has been completed
Plaster installation throughout Building A has begun
Structural Steel for Window Installation in Building C has begun
Installation of Windows throughout Building C's Ground Floor and 1st Floor has commenced
Acoustic Insulation has been installed throughout the intertenancy walls of Building C
Intertenancy Fire Check Plaster is also underway in Building C