Hampton Ltd Construction Update
Hampton Ltd, Hampton
April Construction Update
13 May, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for April 2025.
Hampton Ltd has made significant progress during April, most notably;
- Partial completion of Basement Slab for Building A
- Walls for fire water tanks have been completed
- Some columns across Buildings A & C have been partially erected
- Dincel has arrived on site for internal basement walls
- Lift pits in Building B (Townhomes) have been formed and poured accordingly
- Dincel walls have been erected in Building A for the lift shaft, fire pump room, basement lobby, storage room and bin storage
- The Basement slab of Building B has been partially poured
- Dincel walls have been erected for the garages and lift shafts of Building B
- Formwork has begun in order to pour the Ground Floor slab of Buildings A & B