Hampton Ltd Construction Update
Hampton Ltd, Hampton
February Construction Update
28 February, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for February 2025.
Hampton Ltd has made significant progress during February, most notably Abewolf have;
- Completed the majority of the bulk excavation for both Buildings A & C.
- Detailed all of the piles in order to prepare the basement walls for steel reinforcement as well as Vertical Agi Drains.
- Have completed the install of steel reinforcement on the basement walls of Building A and are near completion of installing steel reinforcement for the basement walls of Building C.
- Have shotcreted the basement walls of Building A and are working their way through Building C. They have troweled the shotcrete in order to give the basement walls a beautiful high end finish compared to a standard basement wall.
- Have completed the site cut for Building B (Townhouses).
- Are currently in the process of completing all piles for Building B.
- Have begun to excavate the elevator pits for Building C as well as begun steel reinforcement for this area which will most likely be poured early next week.