Hampton Ltd Construction Update
Hampton Ltd, Hampton
October Construction Update
30 October, 2024
We are delighted to provide you with the monthly construction update at Hampton Ltd for October 2024.
Hampton Ltd has made significant progress during October, most notably;
- The power authority has completed their internal fitout of the substation. They are now working on de-commissioning the old substation and energising the new one.
- Protection works notices were issued in September, signifying the last approval process required before AbeWolf commence piling and construction on site.
- The internal and external civil design has been submitted to Council for their approval.
- Main works are anticipated to commence after the Melbourne Cup Public Holiday.