Hampton Ltd Construction Update
Hampton Ltd, Hampton
February Construction Update
28 February, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for February 2026.
Rough-in is now officially completed throughout Building A.
Forming of the Roof Terrace of Building C including all reinforcements, has been completed.
All ceiling battens / grids have been completed in Building A in anticipation for plaster.
The roof terrace and hob on Building C have been poured and stripped.
All internal wall partitions throughout Building C have been erected.
The final curved windows in Building A have been installed.
Kingspan ceiling insulation on Level 2 of Building C has been completed.
Blockwork has commenced at the rear of Building C.
LGS frames for Building B have arrived on site, a very big milestone to close out the structure of all 3 buildings!
The main electrical switchboards located in the basement are currently in place and ready to be roughed in.
Rough in of Mech, Fire Services, Plumbing & Electrical has commenced on Levels 1 & 2 of Building C.