Hampton Ltd Construction Update
Hampton Ltd, Hampton
January Construction Update
30 January, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for January 2026.
- Mech, fire services, plumbing & electrical rough in as well as ceiling insulation in near completion in the basement.
- Electrical rough has commenced throughout Building A including sub-boards in common areas.
- Plumbing, fire services & mech are near completion for Building A.
- External windows & doors as well as hardware have been installed throughout Building A Apartments.
- Curved window reinforcements have been fabricated and installed in Building A.
- Rendering has commenced on the parapet of the rooftop of Building A as well as all of the second floor of Building A.
- External waterproofing of some aspects of Building A like door thresholds and balconies has taken place.
- The common area stairs for Building C have been stripped and exposed.
- Level 1, Building C: Fire, Mech and plumbing rough in has commenced.
- All partition walls in Building A have been completed.
- Fire check between the intertenancy walls of Apt 207 & 208 second floor has been partially installed.
- Kingspan ceiling insulation for Level 2 of Building C has been delivered to site and is awaiting installation.
- On the rooftop of Building C we have also formed and reinforced a hob / border which is ready to be poured.