Hampton Ltd Construction Update
Hampton Ltd, Hampton
November Construction Update
30 November, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for November 2025.
Kingspan Insulation to the basement ceiling has commended.
Level 1 Slabworks for Building C Part 2 have been completed. This includes form work, steel reinforcement, plumbing and electrical rough in, post tensioning elements and of course pouring the slab.
Columns and Dincel Walls on Level 1 of Building C Part 2 have been formed, reinforced and poured.
Level 2 concrete deck structure of Building C Part 2, has been completed.
The Dincel Lift Shaft up to Level 2 has also been erected, reinforced and poured.
Propping within the basement of Building C and portions of the Ground Floor have been removed, opening up the space completely which allows you to now visualise the space of the apartments.
Basement: Fire Sprinklers have commenced roughing in. Mechanical ducting/ventilation has commenced. Plumbing rough in has also commenced.