Hampton Ltd Construction Update
Hampton Ltd, Hampton
March Construction Update
2 April, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for March 2025.
Hampton Ltd has made significant progress during March, most notably;
- Capping beams around the entire premises have now been 100% completed.
- Pouring of the fire tank slabs in the basement area of Building C have been completed.
- Currently the steel reinforcement and formwork for the walls of the fire tanks are being completed.
- Bulk Excavation of Building B (Townhouses) has been completed.
- Detailing of all piles located in the Building B area has been completed.
- AbeWolf are currently in the process of completing all piles for Building B.
- Steel Reinforcement as well as vertical agi drains and stormwater points have been completed for the basement walls of Building B, most likely to be shotcreted this week.