Glasshouse Construction Update
Glasshouse, Burleigh Heads
May Construction Update
7 June, 2024
We are delighted to provide you with the monthly construction update at Glasshouse Burleigh Heads for May 2024.
Groupline Constructions continue to make great progress onsite, some noteworthy milestones throughout the month include;
- Structure - 100% complete
- Scaffold - Progressive removal is underway to allow the facade patching and finishing
- Blockwork - 100% complete to level 5 pool area, spa surrounds and stairs
- Concrete stairs from the roof terrace to pool deck is now complete
- Aluminium Glazing - Level 2: 100% complete, Level 4: 80% complete
- Balustrades - Hobs are being finalised ready to measure the baslustrade
- Balcony planters are currently being constructed
- Internal framing - Level 1: 100% complete, Level 2: 100% complete, Level 3: 10% complete
- Internal sheeting - Commencing on level 1
- Joinery is currently in production offsite
- Stone to the feature island benches is being precut on the water jet
- Feature stone vanity prototypes are being constructed and inspected
- Services rough in - Level 1: 100% complete, Level 2: 60% complete, Level 3: 10% complete
- Waterproofing - Level 1: rebates 100% complete, Level 2: 100% complete, Level 3: 80% complete
- Tiling - Tiles currently in storage ready for commencement
- Applied finishes - in progress on the rear precast
- Slab edges are being waterproofed and prepared for render