Cala Dei Construction Update
CALA DEI, Coolangatta
March Construction Update
12 April, 2024
We are delighted to provide you with the monthly construction update at Cala Dei for March 2024.
Some notable accomplishments onsite include;
- Structure - 100% complete
- Scaffold: 100% removed to all sides
- Aluminium Glazing - Levels 11 & 12 - 95% complete
- Internal Framing Level 12 - 100% complete
- Joinery - Level 11 in progress
- Stone - Level 10 in progress
- Internal lobby glass - 90% complete
- Tiling - Level 12 - 95% complete
- Tiling - Level 1 Rec Deck - 70% complete
- Lift Lobbies - 90% complete
- Lift Installation - 100% complete and operational as a builders lift
- External Applied Finishes - 95% complete
- External Screen - Western Side 95% complete, Eastern Side 40% complete
- Service balcony screens - 90% complete
- Padmount Transformer - 100% transferred to apartments
- Level 1 pool - Pool sprayed and awaiting tiling commencement
- Level 1 ceiling to rec deck - 90% complete
- Cross over & footpath to boundary Road - 100% complete