ARC Residences Construction Update
Arc Residences, Toowong
March Construction Update
31 March, 2026
We're excited to bring you this month's update at ARC Residences.
Mostly notably this month;
- Ground: Feature podium structural steel complete. Lightweight framing now 80% complete. With sheeting now well underway.
- Level 1: Defects and builder’s clean underway.
- Level 2: Defecting commencing.
- Level 3: Fit-off complete, with carpet installation beginning.
- Level 4: Builders defects underway.
- Level 5: Builder’s clean complete, ready for defects.
- Level 6: Final fit off complete, ready for builders clean.
- Level 7: Fit off stage underway.
- Level 8: Stone installation underway.
- Level 9: Stone installation set to commence, with wet areas underway.
- Level 10: Joinery install in progress.
- Private Roof Terrace: Planters being waterproofed in preparation for planting.
- Communal roof terrace: Planters being prepared.