ARC Residences Construction Update
Arc Residences, Toowong
November Construction Update
30 November, 2025
We're excited to bring you this month's update at ARC Residences.
Mostly notably this month;
Level 1: U101 Wine room doors installed, services fit-off commenced, stone installation to bathrooms commenced.
Level 2:Tiling in general unit areas nearing completion, grout in bathrooms nearing completion.
Level 3: General unit area tile lay commencing, joinery nearing completion.
Level 4: Carpentry works commenced, joinery loaded in.
Level 5: Sheet, set & sanded.
Level 6: Sheet and set, waterproofing to wet areas.
Level 7: Rough-in partially complete.
Level 8: Glazing nearing completion, framing commencing.
Level 9: Glazing install commenced, C&P set out complete.
Level 10: Blockwork commenced.
Communal Roof Terrace: Pool springs installed.
Penthouse Roof Terrace: Slab poured, blockwork nearing completion, precast verticals installed.